Site Engineering contracted with Douglas County to upgrade an outdated storm drainage system. Approximately 56 linear feet of old corrugated metal pipe was removed and replaced. In addition the project called for multiple concrete box culverts to be installed.

The project included removal of 2 72” corrugated metal pipes and the installation of 4 concrete box culverts, 2 10×10 and 2 8×8, underneath the roadway. In addition was concrete head walls with wing walls and2,700 SF of asphalt was laid in the roadway. This project also called for the removal of trees, bank stabilization with erosion matting, waterline and sewer relocation. 