Big Creek Greenway Phase 1

Location: Roswell, GA
Contract Amount: $3,502,775.54
Owner: Fulton County Department of Public Works

FS22-3

FS22

FS22-1

FS22-2

As part of the Annual Wastewater Service Contract, Site Engineering contracted with Fulton County to rehabilitate 2,009 LF of 48” RCP Sanitary Sewer that was in danger of failing. Site started the project by running CCTV and identifying problem areas. Once that occurred, the pipe was jetted, cleaned, 250 GPM bypass pumping was setup, and HDPE was sliplined into place. Site then performed a post CCTV camera inspection to confirm the repair was to city specifications. This project required two stone check dams on Big Creek, trail repair with GAB, concrete curb and gutter repair, and 10,000 SF of erosion control grassing to restore the construction limit to original condition.

Work Performed:

2009 LF 48” HDPE sliplining
Trenchless Technology
250 GPM Bypass Pumping
Stone Check Dams
Concrete Curb and Gutter
Pre/Post CCTV Inspection
1000 SF Grass Seeding

 

Owner Contact: Sam Tamakloe
SEI Project Manager: David Hess
Previous Project
Manning Drive Sewer Extension
Next Project
Comer Homes- Sanitary Sewer Replacement